Oracle 1z0-076 Question Answer
Examine this list of possible steps:
1. Raise the compatibility level on both databases.
2. Restart SQL Apply on the upgraded logical standby database.
3. Start SQL Apply on the old primary database.
4. Perform a Switchover to the logical standby database.
5. Upgrade the logical standby database.
6. Upgrade the old primary database.
Which is the minimum number of steps in the correct order, to perform a rolling release upgrade of a data guard environment using an existing logical standby database and to enable the new functionality?
Oracle 1z0-076 Summary
- Vendor: Oracle
- Product: 1z0-076
- Update on: Aug 1, 2025
- Questions: 107