VMware 2V0-13.25 Question Answer
An architect is designing a Business Continuity Disaster Recovery (BCDR) strategy for a Virtual Cloud Foundation (VCF) environment with a management domain and multiple workload domains deployed in two datacenters located in the same city.
During one of the initial workshops with stakeholders, the following information was identified:
The Recovery Time Objective (RTO) for workloads is 24 hours.
The management domain must remain continuously available with Recovery Point Objective (RPO) of 0.
Hardware overhead should be minimized by utilizing standby resources that host test workloads during normal operation.
Operational overhead should be minimized.
Latency between both datacenters is 2 ms.
Which design decision should the architect document to satisfy provided requirements?