John is the project manager for a large project in his organization.

John is the project manager for a large project in his organization. A new change request has been proposed that will affect several areas of the project. One area of the project change impact is on work that a vendor has already completed. The vendor is refusing to make the changes as they’ve already completed the project work they were contracted to do. What can John do in this instance?

A.

Refer the vendor to the Service Level Agreement (SLA) and insist that they make the changes.

B.

Review the Request for Proposal (RFP) for guidance.

C.

Withhold the vendor’s payments until the issue is resolved.

D.

Refer to the contract agreement for direction.

ECCouncil 712-50 Summary

  • Vendor: ECCouncil
  • Product: 712-50
  • Update on: Jan 30, 2026
  • Questions: 494
Price: $52.5  $149.99
Buy Now 712-50 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method