When project costs continually increase throughout implementation due to large or rapid changes in customeror...

When project costs continually increase throughout implementation due to large or rapid changes in customer

or user requirements, this is commonly known as:

A.

Cost/benefit adjustments

B.

Scope creep

C.

Prototype issues

D.

Expectations management