A stakeholder has identified a potential scheduling conflict on a current project.

A stakeholder has identified a potential scheduling conflict on a current project. This conflict may affect the completion date by pushing it out two weeks. The stakeholder wants to document this timeline risk.

Which action should the stakeholder take to log the risk?

A.

Log a risk as part of the project business case and identify it as a "schedule" risk.

B.

Log an issue on the project and explain that the completion date is at risk.

C.

Create a task in the project and set the Planned Completion Date for 2 weeks.

Adobe AD0-E903 Summary

  • Vendor: Adobe
  • Product: AD0-E903
  • Update on: Jul 30, 2025
  • Questions: 70
Price: $52.5  $149.99
Buy Now AD0-E903 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method