Given this information regarding a Task:
Planned Start Date: May 14
Actual Start Date: May 14
Planned Completion Date: May 20
Projected Completion Date: May 22
Percent Complete: 50%
Duration: 5 Days
Planned Hours: 8 Hours
Status: In Progress If today ' s date were May 19, what would be the Task ' s progress status?