As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:
. Heavy rainfall affecting the Wellness Garden.
. Local supplier issues causing material delivery delays.
· Dependency on external contractors for hydrotherapy equipment.
The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the
context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.
In addition to the Developers, the teams include:

(The Wellness Garden (a Should Have) is delayed. Sukra Aroon suggests a workaround, using the River Pool Patio instead, and classifying the Garden as a ' Won ' t Have this time ' .
Is this an appropriate suggestion?)