Resources are limited.

Resources are limited. The Sales Manager has two marketing assistants who

may be able to give a few hours a week between them to the project.

What action should the Project Manager take?

A.

Try to secure formal agreement as to how many hours per week the

marketing assistants will spend on the project.

B.

Accept that members of the Solution Development Team will be

inconsistent.

C.

Make each Timebox as long as possible to ensure the marketing

assistants have enough time to complete any work allocated to them

within the boundaries of the Timebox.

D.

Schedule the two marketing assistants to work at different times so they

can hand matters over to one another.

APMG-International AgilePM-Practitioner Summary

  • Vendor: APMG-International
  • Product: AgilePM-Practitioner
  • Update on: Oct 31, 2025
  • Questions: 134
Price: $52.5  $149.99
Buy Now AgilePM-Practitioner PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method