Time is running short and the Must Have requirements for the data entry screenof the...

Time is running short and the Must Have requirements for the data entry screen

of the web page, as recorded in the Prioritised Requirements List, are not going

to be completed on time.

What action should the Project Manager take?

A.

Change the end date of the Timebox.

B.

Ensure that this issue is escalated to the project level roles.

C.

Amend the end date in the Delivery Plan.

D.

Accept that the Must Have requirements will not be delivered on time.

APMG-International AgilePM-Practitioner Summary

  • Vendor: APMG-International
  • Product: AgilePM-Practitioner
  • Update on: Oct 31, 2025
  • Questions: 134
Price: $52.5  $149.99
Buy Now AgilePM-Practitioner PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method