What action should the Project Manager take to plan the deployment activities?

What action should the Project Manager take to plan the deployment activities?

A.

Prepare a Timebox Plan for the next Development Timebox.

B.

Check the Delivery Plan for deployment activities and update as required.

C.

Create a plan of activities to deploy the solution at the end of Timebox C.

D.

Update the Timebox Plan for Timebox C with the activities required to deploy the solution.

APMG-International AgilePM-Practitioner Summary

  • Vendor: APMG-International
  • Product: AgilePM-Practitioner
  • Update on: Oct 31, 2025
  • Questions: 134
Price: $52.5  $149.99
Buy Now AgilePM-Practitioner PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method