Once organizing the work process for RBI program planning has been completed, the next step...

Once organizing the work process for RBI program planning has been completed, the next step is the identification of the:

A.

appropriate mitigation activities that will be considered.

B.

credible damage mechanisms and failure modes.

C.

applicable design and inspection codes and standards.

D.

data and information required to be collected for RBI analysis.