Scope, schedule, and cost parameters are integrated in the:

Scope, schedule, and cost parameters are integrated in the:

A.

Performance measurement baseline.

B.

Analysis of project forecasts,

C.

Summary of changes approved in a period,

D.

Analysis of past performance.