At which stage, in the Tuckman team development model, are team members clear and comfortable...

At which stage, in the Tuckman team development model, are team members clear and comfortable with their roles and responsibilities, and the project manager starts to see signs of the team working together?

A.

Storming.

B.

Forming.

C.

Norming.

D.

Performing