On examining a particular risk in the project there is some uncertainty among the project...

On examining a particular risk in the project there is some uncertainty among the project team of how important this risk is to the project. How would you advise the team on how the significance of the risk is to be determined?

A.

By assessing its probability of occurrence.

B.

By assessing its impact on project objectives,

C.

By assessing both its probability of occurrence and its impact on project objectives.

D.

By assessing its effect on the business case.

APM APM-PFQ Summary

  • Vendor: APM
  • Product: APM-PFQ
  • Update on: Dec 22, 2025
  • Questions: 409
Price: $52.5  $149.99
Buy Now APM-PFQ PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method