During the completion of Job A, £1,000 worth of material was transferred to it from...

During the completion of Job A, £1,000 worth of material was transferred to it from Job B which had finished ahead of schedule.

How will this be inputted into the Job B account?

A.

Job A, £1,000 credit

B.

Job A, £1,000 debit

C.

Job B, £1,000 debit

D.

Job B, £1,000 credit