Zed plc contracted to build an apartment block for Exe Ltd.

Zed plc contracted to build an apartment block for Exe Ltd. Which of the following would provide Zed with a valid excuse not to proceed with the contract?

(i) A key employee who was to manage the project has resigned.

(ii) The price of the materials to be used by Zed plc have increased to such an extent that the building can only be completed at a loss to Zed plc.

(iii) Planning permission has been refused.  

A.

(i) only

B.

(i) and (ii) only

C.

(i) and (iii) only

D.

(iii) only

CIMA BA4 Summary

  • Vendor: CIMA
  • Product: BA4
  • Update on: Jan 31, 2026
  • Questions: 661
Price: $52.5  $149.99
Buy Now BA4 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method