You schedule a time-based single cycle plan with the following assigned planning data:
• Start date for Scheduling: 01.07.2023
• Scheduling indicator: Time
• Call Horizon: 20%
• Cycle Modification Factor: 2
• Cycle/Unit: 10 DAY
What is the resulting call date?