One of the tasks of your project has subtasks.

One of the tasks of your project has subtasks. You wants to restrict time recording to the subtasks.

How can you achieve this in customizing?

A.

Activate task hierarchies with summarization

B.

Activate task hierarchies without summarization

C.

Deactivate the mirrored task indicator for the project type

D.

Deactivate time recording for tasks