When you confirm a task, you wants the system to calculate the difference between planned...

When you confirm a task, you wants the system to calculate the difference between planned work and actual work.

What must you do?

A.

Set the task status to in process

B.

Confirm the task using a completion percentage of less than 100

C.

Ensure that the Rem. Work manually indicator is inactive

D.

Enter an actual finish date of the task in the future