You have created a network with planned work for internal activities.

You have created a network with planned work for internal activities. In a capacity planning report, you discover that no capacity requirements were determined.

What are the possible reasons for this?

There are 2 correct answers to this question.

Response:

A.

A work center has not been assigned to the activity.

B.

The work center does not contain any available capacity data.

C.

The wrong activity type category is entered in the activity.

D.

The indicator calculate capacity requirements is deactivated in the header of the network.

SAP C_TPLM22_67 Summary

  • Vendor: SAP
  • Product: C_TPLM22_67
  • Update on: Aug 10, 2025
  • Questions: 165
Price: $52.5  $149.99
Buy Now C_TPLM22_67 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method