You have created a network with successive activities.

You have created a network with successive activities. After scheduling the network, the Gantt chart shows that every activity has the same earliest start and earliest finish date as the network header. What could be the reason?

Please choose the correct answer.

Response:

A.

The control key is set to no scheduling.

B.

The scheduling type is set to capacity requirements only.

C.

The normal duration of each activity is missing.

D.

There is a loop in the network.

SAP C_TPLM22_67 Summary

  • Vendor: SAP
  • Product: C_TPLM22_67
  • Update on: Aug 10, 2025
  • Questions: 165
Price: $52.5  $149.99
Buy Now C_TPLM22_67 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method