How can you achive a feasible production plan in case of capacity constraints?

How can you achive a feasible production plan in case of capacity constraints?

A.

Select an alternative mode on a resource.

B.

Adjust the available capacity.

C.

Reduce the planning window

D.

Form optimum sequence to reduce setup times

E.

Execute an infinite production planning run