Which of the following is valid sequence of the main activities in production order processing?

Which of the following is valid sequence of the main activities in production order processing?

A.

Creation, availability check, release, material widrawal, confirmation

B.

Creation, release, printing, goods issue, confirmation, goods receipt

C.

Creation, printing, release, goods issue, confirmation, goods receipt

D.

Creation, release, settlement, goods issue, confirmation, goods receipt

SAP C_TS422_2021 Summary

  • Vendor: SAP
  • Product: C_TS422_2021
  • Update on: Jul 31, 2025
  • Questions: 82
Price: $52.5  $149.99
Buy Now C_TS422_2021 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method