A project has a current cost performance index (CPI) of 1.

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

A.

US$S000

B.

US$9500

C.

US$10,000

D.

US$12,500