A project is composed of three phases that are implemented in parallel without affecting one...

A project is composed of three phases that are implemented in parallel without affecting one another. The baselines for each individual phase have been approved by the major stakeholders, and there is a minimal ability to vary the baselines during the execution of the project.

Which methodology did the project manager adopt?

A.

Incremental approach

B.

Predictive approach

C.

Hybrid approach

D.

Iterative approach

PMI CAPM Summary

  • Vendor: PMI
  • Product: CAPM
  • Update on: Feb 21, 2026
  • Questions: 1317
Price: $52.5  $149.99
Buy Now CAPM PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method