A project is in its final stages when a competitor releases a similar product.

A project is in its final stages when a competitor releases a similar product. This could make the project redundant. What should the project manager do next?

A.

Initiate change control.

B.

Address risk mitigation.

C.

Escalate this to the project sponsor.

D.

Initiate project closure.