A project manager has to share a status report with a new stakeholder and is...

A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs lo make this decision?

A.

Organizational process assets

B.

Change management plan

C.

Communications management plan

D.

Resource management plan