A project manager is analyzing a few network diagrams in order to determine the minimum...

A project manager is analyzing a few network diagrams in order to determine the minimum duration of a project. Which diagram should the project manager reference?

A.

A diagram in which resource optimization has been applied.

B.

A diagram in which the critical path method has been applied.

C.

A diagram in which a predefined series of activities has been organized.

D.

A diagram which shows a combination of resource and time optimization.

PMI CAPM Summary

  • Vendor: PMI
  • Product: CAPM
  • Update on: Jul 25, 2025
  • Questions: 1250
Price: $52.5  $149.99
Buy Now CAPM PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method