A Project manager received a change request from a key stakeholder, documented it reviewed it...

A Project manager received a change request from a key stakeholder, documented it reviewed it with the team, and then presented if for decision. What was project manager trying to do?

A.

Develop consensus among stakeholders

B.

Get the budget approved for change

C.

Make sure management is aware of the change

D.

Get approval from the change control board