A project team member is discussing a new project with their manager.

A project team member is discussing a new project with their manager. The project is very similar to a project that was delivered last year and the scope is very well documented.

Which of the following project delivery approaches should be recommended?

A.

Adaptive

B.

Hybrid

C.

Extreme

D.

Traditional