A project team member is estimating the cost of activity and is checking documentation from...

A project team member is estimating the cost of activity and is checking documentation from previous similar projects. Which estimation method is the project manager using to complete this task?

A.

Bottom-up estimating

B.

Three-point estimating

C.

Analogous estimating

D.

Parametric estimating