A recently hired project manager is looking for templates to use for projects on which...

A recently hired project manager is looking for templates to use for projects on which they will work. To what category of enterprise environmental factors should the project manager refer?

A.

Resource availability

B.

Infrastructure

C.

Academic research

D.

Corporate knowledge base