A sponsor asks a project manager to provide a project ' s expected total costs...

A sponsor asks a project manager to provide a project ' s expected total costs based on its progress. What formula should the project manager use to determine this?

A.

Earned value (EV) / actual cost (AC)

B.

Estimate at completion (EAC) - AC

C.

Budget at completion (BAC) / cost performance index (CPI)

D.

EV - planned value (PV)