A subject matter expert (SME) was recently assigned to a project to manage the new...

A subject matter expert (SME) was recently assigned to a project to manage the new compliance requirement. The SME claimed that the activity ' s prioritization needed to change and the schedule could be cut to mitigate the effect of this new compliance need.

How should the project manager proceed?

A.

Perform Integrated Change Control.

B.

Conduct a risk assessment with the team.

C.

Update the schedule to include compliance.

D.

Manage Stakeholder Engagement.

PMI CAPM Summary

  • Vendor: PMI
  • Product: CAPM
  • Update on: May 11, 2026
  • Questions: 1320
Price: $52.5  $149.99
Buy Now CAPM PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method