A team is working on a project using an adaptive approach.

A team is working on a project using an adaptive approach. During project execution, the project gets delayed by one month due to an unforeseen risk. What should the team do next to deliver this project?

A.

Stop working on the project completely, even if the team can continue working on the tasks with the identified risk.

B.

Accept the project delay and add the risk to the lessons learned document for the next project.

C.

Change the delivery date and deliver the initially agreed-upon scope after mitigation of the identified risk.

D.

Reprioritize the work based on the increased visibility of the current risks.

PMI CAPM Summary

  • Vendor: PMI
  • Product: CAPM
  • Update on: Aug 9, 2026
  • Questions: 1337
Price: $52.5  $149.99
Buy Now CAPM PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method