As part of a mid-project evaluation, the project sponsor has asked for a forecast of...

As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?

A.

BAC

B.

EAC

C.

ETC

D.

WBS