Based on a previous project that has been completed, a project manager decides the best...

Based on a previous project that has been completed, a project manager decides the best way to estimate costs is through historical data. What kind of estimating is this?

A.

Three-point

B.

Bottom-up

C.

Parametric

D.

Analogous