During project execution, a team member has identified and then analyzed an opportunity thatwill yield...

During project execution, a team member has identified and then analyzed an opportunity that

will yield a net saving of 10% and reduce time in the schedule by 20%

Which strategy should the project manager adopt to accommodate this opportunity?

A.

Escalate to upper management to build awareness of the opportunity.

B.

Exploit the opportunity immediately, since the cost saving makes it worthwhile.

C.

Transfer the opportunity to a partner and start a partner contract.

D.

Create a trail of the opportunity before full adoption, because of the risk associated.

PMI CAPM Summary

  • Vendor: PMI
  • Product: CAPM
  • Update on: Feb 21, 2026
  • Questions: 1317
Price: $52.5  $149.99
Buy Now CAPM PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method