During the execution of a project, a stakeholder asks a project manager whether the project...

During the execution of a project, a stakeholder asks a project manager whether the project is falling behind or ahead of its baseline schedule. The project manager calculates the earned value analysis (EVA) schedule variance and it comes out to be zero. Which of the following is correct about the EVA schedule variance?

A.

It is calculated incorrectly, as it cannot be zero for an in-flight project; otherwise the project is completed.

B.

Change it to a negative value to show that the project is falling behind.

C.

Zero is a perfectly valid value for an in-flight project; hence share the zero value with the stakeholder.

D.

Change it to a positive value to show that the project is ahead of its baseline schedule.

PMI CAPM Summary

  • Vendor: PMI
  • Product: CAPM
  • Update on: May 11, 2026
  • Questions: 1320
Price: $52.5  $149.99
Buy Now CAPM PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method