Halloween Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmasmnth

The scope management plan is a subsidiary of which project document?

The scope management plan is a subsidiary of which project document?

A.

Schedule management plan

B.

Project management plan

C.

Quality management plan

D.

Resource management plan

PMI CAPM Summary

  • Vendor: PMI
  • Product: CAPM
  • Update on: Oct 24, 2025
  • Questions: 1305
Price: $52.5  $149.99
Buy Now CAPM PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method