When a dynamic systems development method (DSDM) practitioner receives a new high-priority feature request, what...

When a dynamic systems development method (DSDM) practitioner receives a new high-priority feature request, what should the practitioner do first?

A.

Develop the feature as a parallel work package.

B.

Shorten the current work period and begin the new work.

C.

Ask a dedicated team member to complete it immediately.

D.

Prioritize it in the requirements list for the next work period.

PMI CAPM Summary

  • Vendor: PMI
  • Product: CAPM
  • Update on: Feb 21, 2026
  • Questions: 1317
Price: $52.5  $149.99
Buy Now CAPM PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method