When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques...

When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques in this process.

A.

Develop Schedule

B.

Define Activities

C.

Define Scope

D.

Collect Requirements