Which action should the project manager take after the team finishes executing the scope?

Which action should the project manager take after the team finishes executing the scope?

A.

Verify the deliverables to ensure that they are correct and meet the customer's satisfaction.

B.

Accept all the deliverables and deliver them to the customer for final acceptance.

C.

Conduct a joint session with the customer, change the deliverables, and then request approval.

D.

Check that all change requests were implemented and release deliverables to the customer.

PMI CAPM Summary

  • Vendor: PMI
  • Product: CAPM
  • Update on: Feb 21, 2026
  • Questions: 1317
Price: $52.5  $149.99
Buy Now CAPM PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method