Which are inputs for the Plan Quality Management process?

Which are inputs for the Plan Quality Management process?

A.

Quality metrics, project documents, and financial performance

B.

Quality management plan, project documents, and quality metrics

C.

Project management plan, project documents, and organizational process assets

D.

Project management plan, quality metrics. and project documents