PMI CAPM Question Answer
Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?
PMI CAPM Summary
- Vendor: PMI
- Product: CAPM
- Update on: Oct 24, 2025
- Questions: 1305

