How complete should the Sprint Backlog be at the end of the Sprint Planning meeting?

How complete should the Sprint Backlog be at the end of the Sprint Planning meeting? (Choose the best answer)

A.

Enough to ensure there is work for the first few days of the Sprint

B.

The Product Owner will set the threshold for completeness

C.

Every task should be defined

D.

It depends