A business owner has marked certain requirements as high priority for the upcoming release.

A business owner has marked certain requirements as high priority for the upcoming release. After performing some analysis, the project team concluded that some of these requirements are not actually high priority and can be implemented in later releases. How should the project team proceed with prioritizing requirements?

A.

Implement the requirements that the project team considers important.

B.

Execute the requirements that the business owner identified.

C.

Change the priority of the requirements by performing a re-ranking.

D.

Consult with the business owner to discuss possible trade-offs.

IIBA CCBA Summary

  • Vendor: IIBA
  • Product: CCBA
  • Update on: Jul 29, 2025
  • Questions: 638
Price: $52.5  $149.99
Buy Now CCBA PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method