TheScope of Work (SOW)is a project management document that defineswhat services are includedin the work agreement between the sponsor and the CRO or vendor. It outlines deliverables, responsibilities, timelines, and budget allocations.
According to theGCDMP (Chapter: Project Management in Data Management), the SOW includes specifications such as:
The number and frequency ofdata transfers,
Database build and lockmilestones,
Quality control deliverables, and
Resource allocationfor data management tasks.
The SOW does not cover operational site-level details such as monitoring schedules (B), protocol sampling details (C), or personnel contact lists (D).
Therefore,option A (number of data transfers budgeted for a project)correctly identifies a use case directly addressed in the SOW.
Reference (CCDM-Verified Sources):
SCDM GCDMP, Chapter: Project Management, Section 4.1 – Scope of Work and Resource Planning
ICH E6(R2) GCP, Section 5.5 – Sponsor Oversight and Data Management Responsibilities
PMI Project Management Framework – Scope Definition and Deliverable Specifications