In which one of the following circumstances is it recommended to select the Contractor after...

In which one of the following circumstances is it recommended to select the Contractor after a two-stage procurement procedure (pre-qualification + tender procedure)?

A.

When the works are simple and of short duration.

B.

When there is a limited number of capable experienced contractors available and ready to take part in the procurement.

C.

In case of large scale works, where there are several companies likely to have an interest in submitting an offer.

D.

If there is international financing for the project, it is always necessary to conduct a two-stage procurement procedure.

FIDIC CCM Summary

  • Vendor: FIDIC
  • Product: CCM
  • Update on: Jan 7, 2026
  • Questions: 100
Price: $52.5  $149.99
Buy Now CCM PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method