Regarding FIDIC Yellow and Silver Books (edition 1999) the Contractor has submitted its design proposal...

Regarding FIDIC Yellow and Silver Books (edition 1999) the Contractor has submitted its design proposal through the Contractor's Proposal. Which two of the following statements are true in this respect, after it has been submitted?

Choose all of the correct answers (multiple possibilities).

A.

The Contractor is entitled to change the design by optimising the design, without approval of the Employer/Engineer.

B.

The Contractor is not allowed to make any changes regarding the design to optimise the design, unless approved by the Engineer/Employer.

C.

The Contractor may submit a proposal for Value Engineering.

D.

The Contractor is not allowed to submit a proposal for Value Engineering, as any value engineering should already have taken place before submitting its design proposal.

FIDIC CCM Summary

  • Vendor: FIDIC
  • Product: CCM
  • Update on: Jan 7, 2026
  • Questions: 100
Price: $52.5  $149.99
Buy Now CCM PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method